Update Task In Project Flow From P6 To e-Biz fails with ERROR: PROJECT: '<Number>';TASK: '<Number>' ; The task has not been updated. (Doc ID 1335124.1)

Last updated on JANUARY 27, 2017

Applies to:

Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite - Version 2.5 and later
Information in this document applies to any platform.

Symptoms

When attempting to sync projects from Primavera to e-Biz, the following error occurs.

ERROR
-----------------------
PROJECT: '3290_ID';TASK: '5572_ID' ; The task has not been updated.

NOTE: 3920 is the project number in which Task number 5572 has failed. Hence the error may occur for any Project and Task combination.

In more generic, the error will be as follows....
ERROR PROJECT: '<Project Number>_ID';TASK: '<Task Number>_ID' ; The task has not been updated.
OR
ERROR PROJECT: '&PROJECT_ID';TASK: '&TASK_ID' ; The task has not been updated


STEPS
-----------------------
1. Update a Project on Primavera and Sync to e-Biz
2. The Prov ABCS has invoked the Adapter and the API fails with the error

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms