OBIA 11g: ETL How To Run Load Plan In Log Level 6 with BIACM or Scheduling (Doc ID 1605477.1)

Last updated on JANUARY 31, 2017

Applies to:

Business Intelligence Applications Consumer - Version 11.1.1.7.0 and later
Information in this document applies to any platform.

Goal

BI Apps Version: 11.1.1.7
Environment: LINUX
DWH DB: 11G R2
OBIEE: 11.1.1.7.1
ETL: ODI 11G
EBS: Oracle R12.1.3

AIM: We want to capture the Variable values used during the load for debugging the interface execution and make use them in the generated queries.

We have the scenarios below:

  1. Running Load Plan from BIACM
  2. Scheduled the Load Plan to run automatically

In both of the above scenarios we are unable to RUN the loads in Log Level 6.

We do not have the option to run in LOG LEVEL 6.

Could you provide the action plan how we can run the Load in above scenarios in LOG LEVEL 6.

 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms