The XID is not valid start() failed on resource '[connection pool]' (Doc ID 2101675.1)

Last updated on JULY 12, 2016

Applies to:

Hyperion Financial Close Management - Version 11.1.2.4.101 and later
Information in this document applies to any platform.

Symptoms

 The tasks in Financial Close Manager schedules are not starting automatically when the configured start dates for the tasks arrive, nor can users work around the problem by starting the tasks manually.