Calculation Manager Function @CalcMgrDateDiff and Planning Function @HspDateDiff not Calculating Correctly (Doc ID 2268089.1)

Last updated on MAY 23, 2017

Applies to:

Hyperion Essbase - Version 11.1.2.3.500 to 11.1.2.4.008 [Release 11.1]
Hyperion Planning - Version 11.1.2.3.500 to 11.1.2.4.006 [Release 11.1]
Information in this document applies to any platform.

Symptoms

When the start and end dates supplied to the @CalcMgrDateDiff or the @HspDateDiff function span the daylight savings dates, for example March or October when the time changes, the number of days returned by the function is 1 day less than it should be.

This occurs in both 11.1.2.3.50x and 11.1.2.4.00x.

Cause