E1: 13: Estimated Hours & Downtime Not Including Run Machine & Setup Labor from Routing (Doc ID 1265285.1)

Last updated on DECEMBER 05, 2016

Applies to:

JD Edwards EnterpriseOne Capital Asset Management - Version XE and later
Information in this document applies to any platform.
***Checked for relevance on 10-Sept-2012***
System Code: 13C-Condition-Based Maintenance
Executable:P13732 - CAM - Manage Work Order Labor


Symptoms

Estimated Hours and Downtime Hours are not including Run Machine & Setup Labor from the work order routing.  On the Equipment Work Order Routing (P13732) program, details have been entered as follows:

    Run Machine Hours = 5
    Set-up Labor Hours = 2
    Set-up Crew = 3
    Estimated Hours = 12

On the Planning Tab of the Work Order header, the values are:

    Estimated Hours = 4
    Estimated Downtime Duration = 12

The system has not added Run Machine or Set-up Labor Hours to these values. 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms