This document provides answer to some frequently asked questions regarding WIP Revaluation (R30837). Use this document as a supplement to Bulletin E1: 30A: R30837 WIP Revaluation for Standard Costing Document 1510992.1.
Questions and Answers
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Purpose |
Questions and Answers |
Question 1: What is the logic to find material component cost or BOM quantity changes when WIP Reval is called during the cost freeze (R30835)? |
Question 2: How does WIP Reval find subassemblies to include in the revaluation? |
Question 3: What is the logic to find labor rate and/or Routing run labor changes when WIP Reval is call during the cost freeze (R30835)? |
Question 4: If only BOM Quantity changes (and not the item cost) does this trigger a revaluation? |
Question 5: What happens to variance when WIP Reval is run? |
Question 6: What happens if alternate BOMs and Routings are used? |
Question 7: How does WIP Reval calculate A2 costs? |
Question 8: Can a mass WIP Reval be called from R30837 on the menu? |
Question 9: How can Production Inquiry (P31022) numbers and WIP Reval journal entries be validated? |
Question 10: Why does WIP Reval update old work orders that are already closed and not open work orders only? |
Question 11: If AAI 4136 has a blank business unit for the account, where will the system pull the business unit for the account for WIP Reval R30837? |
Question 12: Should the Standard Amount (OPAT) be updated in F3102 if routing and parts list are not attached to the work order? |
Question 13: Why does the R30837 (WIP Reval) have negative signs in the Debit Column? This is confusing to basic Accounting to have negative debits and positive credits. |