E1: UPG: Pristine Package Build After Pristine Upgrade Plan Fails with Data Dictionary Errors (Doc ID 1470957.1)

Last updated on MAY 30, 2017

Applies to:

JD Edwards EnterpriseOne Tools - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

Customer is doing an upgrade from JD Edwards EnterpriseOne XE to EnterpriseOne 9.1 application release level.

Customer is following the suggested best practice to run the upgrade plan for Pristine, apply the Planner ESU and any needed TC ESUs to the Pristine environment, then build a package with these updated objects in the Pristine environment and deploy to the server. This is in preparation for running table conversions on the Enterprise Server.

Cause