Purpose

This document is part of an Information Center - to see other documents related to Job Cost & Change Mgmt, please use the following links: Information Center: Overview of JD Edwards EnterpriseOne Job Cost & Change Mgmt > Information Center: Using JD Edwards EnterpriseOne Job Cost & Change Mgmt > Document 1520297.1

This information will help Job Cost users and Information Technology Staff understand how to Update Percent Complete (P511112).  This document assumes that that job cost constants, ledgers, job, and accounts have been set up correctly and conform to the required standards.  It also assumes that the Profit Recognition Build has been run in final mode.  If additional information is needed on the above topics, the related Knowledge Documents are listed below. 

Scope

Job Cost Users Information Technology Staff should find this document helpful when trying to understand how to Update Percent Complete.  It will help with the understanding of the main concept of Update Percent Complete and how it relates to the Job Cost system.  It is not intended to be a review of the entire Job Cost System and all options that are available.

Details

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Purpose
Scope
Details
 Overview
 Job Cost Setup Review
 HA Ledger
 F% Ledger
 Single/Group Job Adjustment (Profit Recognition Master G5122/P5144)
 Threshold % Complete
References