E1: 51: Budget Totals for Method of Computation (MOC) I when using MOC H, L, and I (Performance Based Labor Progress Entry) (Doc ID 1612900.1)

Last updated on NOVEMBER 23, 2015

Applies to:

JD Edwards EnterpriseOne Project Costing - Version XE and later
Information in this document applies to any platform.

Symptoms

Currently, when using a Job that uses Method of Computations (MOC), "H", "L", and "I" and Budgets are entered on the detail "I" Level, the system does not roll
them to the "L" Level.  Currently, actuals that are added at the "I" detail lines roll up to the "L" level.  This enhancement request will need to be completed before budgets that are entered on the "I" Level roll up to the "L" Level.

 

Cause