E1: 34: Level Lead Time to be Used for E/D Message by MRP Process (Doc ID 1618031.1)

Last updated on DECEMBER 23, 2015

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms


On :  9.1 version, MRP (R3482)

ACTUAL BEHAVIOR  
---------------
When Work Order fields DRQJ & STRT are set manually, E and D messages will use different lead times for the calculation of RRQJ (Recommended Completion Date) and RSTJ (Recommended Start
Date).

In case of Message Type E, the recommended start date will be calculated using the WO lead time.
Note: WO lead time here means calculated from manually set  WO DRQJ & STRT.

In case of Message type D, recommended start date will be calculated using LeadTime(LTVL) from the Item Branch record (P41026)

EXPECTED BEHAVIOR
-----------------------
Expedite message should be generated based on LTVL like D message.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms