E1 : 43:Adding New Line To Received PO While in Receipt Routing is Triggering Approvals (Doc ID 1640975.1)

Last updated on FEBRUARY 11, 2016

Applies to:

JD Edwards EnterpriseOne Procurement and Subcontract Management - Version 9.1 and later
Information in this document applies to any platform.

Symptoms


Approval route and receipt routing are set up for this scenario. After receiving line(s) from a purchase order and moving the receipt to intermediate step in the route (INSP), if the user adds a new line in the order, the status of the previously received lines will change to awaiting approval. After approving the order a second time, the original line will no longer reflect the fact that it was received.

Cause

Sign In with your My Oracle Support account