E1: 33: CRP - R3382 back scheduling the load into wrong period (Doc ID 1663973.1)

Last updated on DECEMBER 23, 2015

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms

When there exists multiple routings and CRP is run for E and D messages selecting the first routing work center only by data selection,
CRP is not back scheduling the load into the correct periods for the first routing work center.
Routing step dates from a CRP run are not correct when messages exist to change the dates of existing work orders with routings already attached.

Cause