E1: 30L: The Calculation Of “Value Added Time” Of The Process With Overlap Is Incorrect

(Doc ID 1681579.1)

Last updated on DECEMBER 10, 2015

Applies to:

JD Edwards EnterpriseOne Demand Flow Manufacturing - Version 9.0 to 9.1 [Release 9.0 to 9.1]
Information in this document applies to any platform.

Symptoms

9.0 Demand Flow PF30L910 Line Design with TPCT Calculation - When a process has both Labor and Machine time the values are being added to calculate Value Added Time when only the longest of the two values should be used. (Example Labor = 2.0 minutes, Machine = 3.5 minutes, the expected result is 3.5 per the manual but the calculated result is 5.5)

Cause