E1: 31P: F4801T.PLMR Not Updated By R31802A (Doc ID 1913901.1)

Last updated on DECEMBER 16, 2015

Applies to:

JD Edwards EnterpriseOne Engineer to Order - Version 9.0 to 9.1 [Release 9.0 to 9.1]
Information in this document applies to any platform.

Symptoms

ISSUE IDENTIFICATION
Application Release: 9.0
Program impacted: R31802A / P31P001 / Job Cost
Tools Release:
Platform/Server:



ISSUE
R31802A does not update the F4810T records. As a result the F3102 Planned Material Amount (A1/PLAT) cab be different to the F4801T OACM and PLMR.
ETO Planned Material Amounts come from F4801T.PLMR.

Budget upload to Job Cost uses the F3102 amounts (and not the F4801T amounts). As a result it is possible to have Job Cost Budget (F0902), Planned ETO Cost (F4801T), and WO Planned Cost different (F3102). As P4310 and P3111 also update F3102 (between R31802A runs) the difference in the amounts can cause significant end user confusion.
This then means that there is a difference between the Budget (Planned) Amount in Job Cost and the Planned Amount in ETO.

EXPECTED BEHAVIOR
Desired Outcome
The Planned amount in the WO Cost File, the Planned Amount in ETO Workbench and
1. The Planned Cost in WO Cost File to be the same as the Planned Cost in ETO Workbench. and
2. The Planned Cost in ETO Workbench to be the same as the Budget (Planned) Cost in Job Cost, immediately after any Budget upload, R31P800.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms