E1: 31: Requested and Start Dates on Routing are Two Days Before WO Start and Req Dates (Doc ID 1916699.1)

Last updated on DECEMBER 15, 2015

Applies to:

JD Edwards EnterpriseOne Configurator - Version 9.0 to 9.0 [Release 9.0]
Information in this document applies to any platform.

Symptoms

JD Edwards EnterpriseOne : 9.0 version, Work Order Processing

P3112 routing

Tools Version 8.98

ACTUAL BEHAVIOR
---------------

Using fixed leadtime and leadtime per unit = 24 without running leadtime rollup the two operation routing is calculating the start date and requested dates two days before the work order start date and requested date for the first operation.

EXPECTED BEHAVIOR
-----------------------
To have the routing requested and start date calculated the same for each routing operation

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a manufactured item
2. In additional systems information populate Fixed leadtime and leadtime per unit = 24
3. Create a simple BOM with one item
4. Create a Route for two operations with labor hours on the first operation
5. Create a work order for a future requested date
6. Attach the parts list and routing via interactive or R31410
7. Check the start dates and requested dates of the two routing steps
8. The second operation is one day before the work order requested date but the first operation is two days before the work order requested date


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms