E1: 34: Add Processing Options To R3482 And R3483 For Alternate Forecast Consumption Periods

(Doc ID 1922698.1)

Last updated on NOVEMBER 15, 2017

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

Can Forecast Consumption be set up so that different Branch Plants (or different items, or groups of items) can consume in different consumption periods? For example some Branchs would like to use Forecast Consumption with weekly consumption buckets while others would like to consume the forecast in a monthly or quarterly bucket. Currently MRP will use the dates that are set up in P3405 but all versions of MRP will see the same dates. 

Cause