E1: 34: Promised Ship Date Is Less Than Today When Using Delivery Date and Branch Plant Relationships (Doc ID 1939997.1)

Last updated on DECEMBER 16, 2015

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.0 to 9.1 [Release 9.0 to 9.1]
Information in this document applies to any platform.

Symptoms

When processing an Order & Expedite (B) message in MRP Message Detail (P3411) for an Order Transfer (OT) message that has a Request Date between today's date and the Transit Lead Time as defined in a Delivery Date Preference (09) for the Branch and Supplier, the resultant Sales Transfer Order (ST) is created with a Scheduled Pick Date after the Ship Date.

 