E1: 31A: Data Selection for R31802A Does Not Include Work Order Completion Date STRX (Doc ID 1953265.1)

Last updated on DECEMBER 23, 2015

Applies to:

JD Edwards EnterpriseOne Shop Floor Control - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

Currently data selection for Manufacturing Accounting UBE R31802A does not include Work Order Completion Date STRX from Work Order Master (F4801) file.
Suppose in the month of December we need to run accounting for Work Orders completed in November by setting the G/L Date in R31802A Processing Option to November. Since we cannot restrict the data selection by Work Order Completion Date, system will pick all the work orders at the specified status including the ones completed in December and post them to G/L Date in November.