E1: 31: Routing (P3112) Operations Dates Stop at 12/31/2014 and No Recalculation on Routing If WO Header Is Changed (Doc ID 1957553.1)

Last updated on DECEMBER 23, 2015

Applies to:

JD Edwards EnterpriseOne Shop Floor Control - Version 9.0 and later
Information in this document applies to any platform.

Symptoms

E1 9.0 / Shop Floor Control
P48013 Work Order Entry w/Recalculation

1. Work Order Routing (P3112) Start (STRT) and Request (DRQJ) dates remain in 2014 regardless of actual work order (header) due date (DRQJ).  
All routing step dates are then backscheduled from 12/31/2014 (last routing step).  This occurs if either the batch R31410 or interactive method
is used to attach the routing.

2. With the P48013 Quantities and Dates processing option (Validating tab, option #1) turned 'on' to recalculate the Parts List (P3111) and Routing
(P3112) information and revising the work order header Quantity (UORG) or Request (DRQJ) date, the work order header information and parts list
Request Date is correctly recalculated.  However, the Routing (P3112) quantity and dates are NOT recalculated in the case of a WO header Request
Date change and incorrectly recalculated in the case of a WO header Quantity (UORG) change.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms