Symptoms

R31410 – Work Order Processing
P311221 – Hours and Quantities Update

A configured item has multiple configured sub-assemblies and routings.
There are 2 Operation sequences “10.00” in the WO routing because they are pulled from different sub-assemblies and the work centers are different.
WC1 - OP Seq # 10 - assembly (populated from the parent cfg item)
WC2 - OP Seq # 10 - forging (populated from the sub assembly CFG item)

When doing H & Q update (P311221) for the WO routing Op Seq#10, the system is considering the first operation sequence encountered in the F3112. Using the older version (XE), it used to re-sequence the operation sequences of configured children sub-assemblies and assign unique operation sequence numbers.
On the P311221 it cannot be entered any record against a particular Work Center.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms