E1: 34: PMPN Messages are Incorrect When WO Has Dates Earlier then Demand (Doc ID 1990169.1)

Last updated on AUGUST 31, 2016

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

When planning items with Production Numbers (PMPN) when the Work Orders are moved in to an earlier date with out adjusting the related SO date the following problems occur:

1.  If the WO is Frozen or Past Due a new O (Order) message is created to match the SO demand quantity and date.
2.  If the WO is Past Due compared to the System Date and the Parts List is attached then no Order message is created for the components. If an open order exists for the components it gets a Defer message to meet the demand of the new Planned order that was created in error.
3.  If there is an open order for the components which is Frozen but the Parent WO is not Frozen the order will get both an F (Frozen) message and a D (Defer) when only the F message is expected.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms