E1: 34: R3483 Suggests New PLO with Supply Inside Defer Damper Days (Doc ID 2011200.1)

Last updated on DECEMBER 16, 2015

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms

E1 9.1 / R3483

If there is demand after a Work Order or Purchase Order but these lie within the damper days specified in the processing options of R3483, MRP correctly does NOT defer the Work Order or Purchase Order but the supply is not considered and an incorrect PLO is suggested to meet the demand.

Cause