Symptoms

On : 9.1 version, MRP

It seems that if multiple demands exist inside the current Periods of Supply Horizon ( item uses OPC =4 ) ,  R3483 incorrectly suggests a PLO at start of the Horizon and correct Ending Available is not calculated correctly and hence Beginning Available at start of next Periods of Supply horizon is incorrect in P4021.


However, the Time series is ok and R3482 yields correct results.