E1: 49: Freight Update Called After Cancelling a Receipt (Doc ID 2023583.1)

Last updated on AUGUST 08, 2017

Applies to:

JD Edwards EnterpriseOne Transportation Management - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms

When a user realizes they are unable to receive a PO because the material is
not available, they press the cancel button in P4312, but Freight Update is
still called right after that. At that point, if they press ok instead of
cancel, freight update runs even through the PO has not been received. Then
when they are ready to receive the shipment, they cannot do it through the
normal process because the shipment is at a status '80', and then have to
receive the PO directly in P4312. This request is for the process flow not
to call R4981 if the user cancels in P4312 instead of completing the receipt.
It should just take them out of the receiving program (P4915) altogether.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms