E1: 30A: New Total WIP Cost On R30837 Is Incorrect For Work Orders With Outside Operations (Doc ID 2028882.1)

Last updated on MAY 31, 2016

Applies to:

JD Edwards EnterpriseOne Product Data Management - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms

DESCRIPTION OF PROBLEM
======================
WIP Reval does not update Outside Operation in F3102 for Standard and Completed when a new Outside Operation is added to the routing.

STEPS TO REPRODUCE
==================
Enter parent and component items
Set up *OP items in item master and branch plant M30 for *OP10, *OP20, *OP30, *OP40, *OP50
Set up D1 - D5 in UDC 30/CA - confirm special handling code se to "1"
Enter P4105 08 cost for component and all *OP items

Enter BOM with one per of component item on Op Seq 5

Enter Routing with direct labor hours on Op Seq 5
Outside operations for Op Seq 10 and 20
Final Op Seq 90 with Machine hours

Simulate and Freeze, Data selecting the Parent and all *OP items
Note only the *OP 10 and 20 are included in the parent item

Enter a work order QTY 10

Next change the Item routing and add another outside op *OP30

Run R31410 and attach parts list and routing and generate purchase orders

Review F3102 and see that Standard has costs for *OP10 and *OP20
Current has costs for *OP10, *OP20, and *OP30

In the work order routing, add Outside operations for operation sequences 40 and 50

From drop down menu go to purchase orders and generate POs for *OP40 and *OP50

Run R31802A in proof to generate planned costs in the F3102
Review F3102. NO planned costs are populated in the F3102 for the outside operations. A Bug was entered for this issue.

Issue all material
Receive all 5 purchase orders
Enter 4 HRs B1 labor (Op Seq 5) and 8 HR B3 time (Op Seq 90)
Complete 5

Run R31802A in final

Review F3102 and see that the Actual and Completed columns are populated.
All costs as expected except as noted above

Simulate, then freeze, calling WIP Reval. Note that *OP 30 should be included in the new parent cost.

Standard and completed did not get updated for the addition of the D3 cost which was part of the new frozen cost.
Actual and planned are cleared for D4 and D5

DESIRED OUTCOME
===============
Standard and Completed should include the new Outside operation in the F3102.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms