E1: 31P: P31P001 Forward and Back Schedule Related Purchase Order Dates (Doc ID 2046498.1)

Last updated on DECEMBER 16, 2015

Applies to:

JD Edwards EnterpriseOne Engineer to Order - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms

On : 9.1 version, Engineer to Order P31P001
Forward and Backward Schedule

The ETO Net Change Processing R31430 from ETO workbench P31P001 processes task dates for a backward or forward schedule update but does not adjust the related order dates accordingly.  This means that related supply orders will
not be adjusted as needed for the schedule change. 

Cause