E1: 31P: P31P001 Forward and Backward Schedule ETO WO Parts List Related Purchase Orders Enhancement Request (Doc ID 2051593.1)

Last updated on DECEMBER 16, 2015

Applies to:

JD Edwards EnterpriseOne Engineer to Order - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

On : 9.1 version, Engineer to Order
P31P001 Forward and Backward Schedule

The forward and backward schedule logic in P31P001 does not reach down to the production work order parts list detail line, related purchase order dates.  This means that P3111 related supply orders will not be adjusted as needed for the schedule change.  