E1: 43: Partial Receipt In Another UoM Does Not Update The Original Line Accordingly (Doc ID 2057605.1)

Last updated on JULY 15, 2016

Applies to:

JD Edwards EnterpriseOne Procurement and Subcontract Management - Version 9.1 to 9.2 [Release 9.1 to 9.2]
Information in this document applies to any platform.

Symptoms

When doing a partial receipt in another unit of measure, the original line is split. The new line added is for quantity received and has a next status of 999. The open quantity and open amount from the original line remain unchanged, which is incorrect.

Cause

Sign In with your My Oracle Support account