E1: 33: Review Work Center Load Is Showing Incorrect Capacity (Doc ID 2065002.1)

Last updated on DECEMBER 10, 2015

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms

Issue in E1: 9.1 / T.R: 9.1
Application: P3313 - Work Center load
----------------------------

ACTUAL BEHAVIOR
---------------
Work center is having a holiday from 01-Aug-2015 till 16-Aug-2015. Resource units are generated appropriately.
Running R3382 on 29-July 2015 shows the incorrect Gross Capacity, Rated Capacity, Available Capacity, Accum. Available capacity for 17-Aug-2015

EXPECTED BEHAVIOR
-----------------------
Expected to see the correct gross capacity.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:


1. Create a work center PR-201 with 7 hours shift
 
2. Run R3007G refresh units to generate resource units
 
3. Verify that Refresh units are collected as per the work day calendar.
Note that particular resource is set to have resource units from 17 to 21, 24 to 28, 31

4. Run R3382

5. Review work center load & verify that 08/17/2015 is showing incorrect capacity.
As per refresh units it is expected to show 7 hours but it shows 77 hours

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms