E1: 31P: PRP Planned Phantom Components Linked To Top Level Of Project Not Parent Of Phantom (Doc ID 2065365.1)

Last updated on MARCH 22, 2016

Applies to:

JD Edwards EnterpriseOne Engineer to Order - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms

On : 9.1 version, Engineer to Order

P31P001When processing the O supply order message for a Parent Item that has a phantom component, the phantom component supply messages are not updated with the change in source of demand.  Only the phantom supply order message (informational or optional message) is updated with the newly created firm order as the new source of demand. 

Cause