E1: 31: How to Setup Work Center to Allow Load Balancing for Multiple Equipments (Doc ID 2071562.1)

Last updated on FEBRUARY 01, 2016

Applies to:

JD Edwards EnterpriseOne Shop Floor Control - Version 9.1 and later
Information in this document applies to any platform.

Goal

How can we set up the following scenario:

- We have a WO of 100 items. In the first phase the 100 units are completed in one machine->OK.
- In the second step, 50 are completed in one machine, and the other 50 in another machine. The two machines are equivalent (one is faster than the other)->how to set up this scenario?
- In the next steps, 75 are completed in one machine, and the other 25 in another. The two machines are equivalent (one is faster than the other)->how to set up this scenario?

 


 

Solution