E1: 30A: P30026 Displays Wrong Cost Calculation for Multiple Routings with Different Effective Dates (R30812) (Doc ID 2080677.1)

Last updated on DECEMBER 16, 2015

Applies to:

JD Edwards EnterpriseOne Product Data Management - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

When accessing Row Exit -> Cost Calculation from P30026 Cost Component application, the calculation is not working correctly for different as of dates.

Consider the following scenario:
Setup new routing with effective date 11/16/2015 to 12/31/2040 and expire routing 1/1/2015 to 11/15/2015.
Run R30812 with as of date 11/1/2015 and P30026 displays the correct simulated cost for 11/1/2015.
Rerun R30812 with as of date 11/16/2015 and this also displays the correct simulated cost for 11/16/15 and when accessing row exit to 'Cost Calculation', the form displays calculation for 11/16/2015 which is correct.
Rerun R30812 with as of date 11/1/2015 and P30026 displays the correct simulated cost for 11/1/2015 but when accessing row exit to 'Cost Calculation', the form displays calculation for 11/16/2015 and not calculation for 11/1/2015.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms