E1: 34: Sequence Branch Plant by Supply Chain Levels (Doc ID 2082045.1)

Last updated on OCTOBER 24, 2016

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms

On : 910 version, MRP R3483

ACTUAL BEHAVIOR
---------------

The multiplant MRP program (R3483) planning is impacted by the alphanumeric sort order of the branch plant, 10 and 20 or M10 and M20. Demand plant planning does not consistently drive supply plant messages, as if dependent on the alphanumeric sequence.