My Oracle Support Banner

E1: 34: Sequence Branch Plant by Supply Chain Levels (Doc ID 2082045.1)

Last updated on JANUARY 09, 2018

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 to 9.1 [Release 9.1]
Information in this document applies to any platform.

Symptoms

On : 910 version, MRP R3483

ACTUAL BEHAVIOR
---------------

The multiplant MRP program (R3483) planning is impacted by the alphanumeric sort order of the branch plant, 10 and 20 or M10 and M20. Demand plant planning does not consistently drive supply plant messages, as if dependent on the alphanumeric sequence.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.