E1: 46: Requirement to run R46471 as a Subsystem Job

(Doc ID 2111824.1)

Last updated on JULY 12, 2016

Applies to:

JD Edwards EnterpriseOne Warehouse Management - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

 ********************
E1 Release: 9.2
Program ID: R46471
Platform/Server/Environment:
Tools Release: 9.1
***************************

---------------
Customer is running the R46171 in subsystem, but then has different set up for the processing in R46471 depending on the area of the warehouse that the suggestion is created for. In other words once the R46171 is run and the locations are assigned a more warehouse specific processing is required with several version of R46471 being executed with different data selection.
The reason is that in the warehouses customer is using a mix of paper picking (which would require to process R46472 and R46473 for these zones) as well as electronic interfaces for automated hardware (where only R47471 is run) as well as RF-SMART where again specialized requirements are in place.

The request is to review the current design of R46171/R46471 from this perspective and to provide the flexibility and variation of allowing to run the R46471 as a separate subsystem job. This would allow R46171 to be an initial subsystem job to service all the 'front end' programs and determine the locations and warehouse zones, and then to allow R46471 to be a separate subsystem job to use the required data selection to perform specific processing for the warehouse zones etc.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms