E1: 51F: Display Header Units and Metrics in Forecast

(Doc ID 2134073.1)

Last updated on MAY 04, 2016

Applies to:

JD Edwards EnterpriseOne Advanced Job Forecasting - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

In the detailed forecast P51F100 for a job, display in separate columns the cost code header units and header unit of measure similar to the way header units and header unit of measure columns are displayed in JSI (Job Status Inquiry) in Job Cost.

Provide 9 calculated columns:
For each record in the grid, perform the following calculations:
Budgeted Amount per unit = RBLA / (RBLU Header Quantities)
Budgeted Units per UOM = (RBLU Header Quantities) / RBLU
Budgeted UOM per unit = RBLU / (RBLU Header Quantities)
Actual Amount per unit = (Actual Amount (AA)) / (Actual Header Quantities)
Actual Units per UOM = (Actual Header Quantities) / (Actual Units (AU))
Actual UOM per unit = (Actual Units (AU)) / (Actual Header Quantities)
EAC Amount per unit = (Revised Projected Final Amount) / (EAC Header
Quantities (HU))
EAC Units per UOM = (EAC Header Quantities (HU)) / (Revised Projected Final
Units)
EAC UOM per unit = (Revised Projected Final Units) / (EAC Header Quantities
(HU))


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms