E1: 43: P4312 Writes Zero Landed Cost Records in F4111 Cardex Depending on P41291 Cost Position (Doc ID 2138670.1)

Last updated on MARCH 27, 2017

Applies to:

JD Edwards EnterpriseOne Procurement and Subcontract Management - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

Zero amount landed costs are written or not in F4111 depending on the setup position in landed cost rule P41291.
If landed cost is set in P41291 with zero percentage on LAST row, after purchase order receipt, a record with zero amount will be written to F4111.
If landed cost is set in P41291 with zero percentage on a row in the MIDDLE, after purchase order receipt, no record with zero amount will be written to F4111.

Cause