E1: 13: Parts List Component Rev Defaulting From Item Branch Not Bill Of Material (Doc ID 2148202.1)

Last updated on JUNE 09, 2016

Applies to:

JD Edwards EnterpriseOne Shop Floor Control - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

When running the R31410 (Work Order Generation) report and attaching a parts list to the work order, the item component rev (CMRV) is defaulting from the Item Branch (F4102) not the bill of material (F3002)

Cause

Sign In with your My Oracle Support account