E1: 74U: Discrepancy Between Application (P74U0420) And Certificates (P74U0425) Entry

(Doc ID 2175146.1)

Last updated on SEPTEMBER 05, 2017

Applies to:

JD Edwards EnterpriseOne Procurement and Subcontract Management - Version 9.1 to 9.2 [Release 9.1 to 9.2]
Information in this document applies to any platform.

Symptoms

When adding an application via SPC - Application Maintenance (P74U0420) and enter only one of the following values:

Application Quantity or Application Amount or App. Cum Quantity or Appl Cum amount, all other blank cells are auto-calculated.


However, when it comes to entering certificates via SPC - Certificate Maintenance (P74U0425) and enter only one of the following values:

Certificate Quantity or Certified Amount or Cumulative Certified Qty or Cumulative Certified Amt, the system does not calculate the other cells.

Furthermore, some errors occurs.

ERRORS
-----------------------
74U223 - Period and Cumulative amounts mismatch
74U419 - Certified Amounts NOT Entered


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms