E1: 51: R5112(Forecast Summary Creation) Calculates Incorrect Spread For The Last Period (Doc ID 2179121.1)

Last updated on OCTOBER 23, 2016

Applies to:

JD Edwards EnterpriseOne Project Costing - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

When R5112(Forecast Summary Creation) is executed the spread for the last period is calculated incorrectly.

It takes the entire month spread instead of the planned completion date.