E1: 34 F4102 MRP Net Change Flag Not Set With Sales Order Status Change (Doc ID 2200102.1)

Last updated on NOVEMBER 02, 2016

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 to 9.2 [Release 9.1 to 9.2]
JD Edwards EnterpriseOne Sales Order Processing - Version 9.1 to 9.2 [Release 9.1 to 9.2]
Information in this document applies to any platform.

Symptoms

When a Sales Order is entered or the Status is changed using P4210 the F4102 Net Change Flag is not updated. If the SO Status is updated by the R42565 the F4102 Net Change Flag is not updated. Any time that the SO Detail line is changed (shippable or back-ordered quantity, transaction unit of measure, branch/plant, lot, requested date, pick date, or next status) the F4102 Net Change Flag must be updated so that the next run of a Net Change version of MRP will re-plan the item.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms