Symptoms

On : 9.1 version, Localizations - JAPAC - Procurement
P31114 WO Completions

ACTUAL BEHAVIOR
---------------
When performing the work order completion for any user defined work order type, the record is incorrectly updated in F75I008.


STEPS
-----------------------
1.In P40040 create a user defined work order type W1.
2.Create the receipt routing definition using P43091.
3.Create a supplier item relationship using P43090 for the india localization item and b/p.
4.Create a work order using P48013 for this type W1.
5.In the processing options of P31114 enable the receipt routing processing option.
6.Query the W1 order in P31114. Select it, populate the qty completed and click Save and Close.
7.Notice that this work order is incorrectly updated in F75I008.
8.However notice that completions for standard work order types “WO” donot get updated in F75I008, which is correct.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms