Symptoms

Copy an existing project which has some WO tasks using ETO workbench(P31P001). Tasks in the project are closed and have lot numbers(LOTN) in WO header table(F4801).  New project that has some WO tasks is added.

Check these new added WO tasks that are created from closed WO tasks. Lot numbers(LOTN) in WO header table(F4801) have been populated for these new WO tasks. Lot numbers are as same as them in closed WO tasks.


When a WO task in an existing project has not been processed by R31802A, the WO task has completed quantity in Unaccounted Direct Labor Hours (CTS1.F4801). In case of copying a project that has the above WO task,  not only Lot number but also Unaccounted Direct Labor Hours (CTS1.F4801) are copied to new added WO task in a new project.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms