E1: 49: Inconsistent Consolidation Results When Entering ship Date On Different Lines (Doc ID 2231353.1)

Last updated on AUGUST 15, 2017

Applies to:

JD Edwards EnterpriseOne Transportation Management - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

********************
E1 Release: 9.1
Program ID: P4210
Platform/Server/Environment:
Tools Release: 9.1
***************************

When entering orders with multiple lines with Single Order consolidation and depending whether dates are populated on the first or second line the consolidation results are different.
Test 1:
Enter multiple line Order and populate Promised Ship (PPDJ) date on line 1 however no date on line 2 and line 3 and all lines end up on the same shipment, which is incorrect.
Test 2:
Enter multiple line Order and let dates default on line 1 and populate Promised Ship date on line 2 then both lines end up on different shipments which is correct.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms