E1: 51: P51901 System Allows Incorrect Planned Finish Date in P51901 Application Greater than Planned Completion Date in P51006 Application
(Doc ID 2232330.1)
Last updated on FEBRUARY 04, 2019
Applies to:
JD Edwards EnterpriseOne Project Costing - Version 9.1 and laterInformation in this document applies to any platform.
Symptoms
System does not throw an error message when the planned finish date entered in Cost Code Schedule Revision application is greater than the planned completion date in P51006 application. This causes incorrect forecast values in summary forecast.
Cause