E1: 34: MRP Ignores PMPN Purchase Orders with Effective Date Falling on a Non-work Day (Doc ID 2273635.1)

Last updated on JUNE 24, 2017

Applies to:

JD Edwards EnterpriseOne Requirements Planning - Version 9.1 and later
Information in this document applies to any platform.

Symptoms

R3482 - MRP Single-Plant

When using MRP for planning Production Number items, MRP ignores any existing PMPN purchase orders with Planned Effective Date on non-work day and creates new O or B messages for the same PMPN demand.
That leads to double supply for the same PMPN demand line.

Cause