E1: 07: R07810 Number of Weeks Worked calculation incorrect with "Any Time Card Equal to Week Setting" (Doc ID 2280002.1)

Last updated on JUNE 23, 2017

Applies to:

JD Edwards EnterpriseOne US Payroll - Version 9.0 and later
Information in this document applies to any platform.

Symptoms

When the Quarterly Weeks Worked Report (R07810) is set to process the weeks worked calculation by any time card is equal to a week (process option 2 on process tab of R07810 = 2) the calculation is Not correct. The calculation
appears to be doubling the number of weeks worked.

Cause