Symptoms

Using Periods of Supply purchased items and a supply purchase order exists with a past due date. R3483 - Multi-Plant MRP, MRP triggers a correct Defer message to meet the existing future customer demand. However, the Recommended Start Date, Recommended Complete and Recommended Effective Date for the Defer message triggered for the past due supply order is incorrect, as it's the MRP Generation Date (e.g. today's date) instead of actual Scheduled Pick Date of the SO demand.