E1: 46: Manual Planner Open Quantity Goes Negative When Editing Quantities

(Doc ID 2292508.1)

Last updated on SEPTEMBER 14, 2017

Applies to:

JD Edwards EnterpriseOne Warehouse Management - Version 9.2 and later
Information in this document applies to any platform.

Symptoms

In the following scenario, quantities are not updated correctly:

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Error can easily be duplicated by going into P4600,
2. Click Find on Status 200,
3. Row Exit to Manual Planner
4. Use Visual Assist to find available Lot and Location
5. Enter Quantity Less that Requested quantity
6. Add another Line at a Quantity less than or equal to the remaining Open Quantity
8. Edit Quantity on either Line 1 or 2
9. Open Quantity does not recalculate correctly, It displays a negative number.


Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms