E1: 31P: Status 99 of a Completed WO Task is Updated Back to 40 by Executing Process Project in More Project Action

(Doc ID 2294740.1)

Last updated on SEPTEMBER 10, 2017

Applies to:

JD Edwards EnterpriseOne Engineer to Order - Version 9.1 to 9.2 [Release 9.1 to 9.2]
Information in this document applies to any platform.

Symptoms

There are 2 WO tasks in a project. One is for  WIP item. Another is for  final product. WO task for a WIP is completed. And its status is 99. Next, execute Process Project in More Project Action for the WO task for final product to attach parts list and routing.

After that, the status of WO task for a WIP is changed to 40 from 99.

R31410 version set in ETO workbench (P31P001) processing option has a condition that WO status is equal to 10. So the WO task for a WIP should not be processed by R31410.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms