E1: 51: Row Exit to Update Percent Complete (P511112) from Job Master (P51006) Only Allows Changes to Highlighted Record (Doc ID 2296441.1)

Last updated on AUGUST 11, 2017

Applies to:

JD Edwards EnterpriseOne Project Costing - Version 9.2 to 9.2 [Release 9.2]
Information in this document applies to any platform.

Symptoms

When a user highlights a job in P51006 and takes the row exit to Update Percent Complete, only the job highlighted in P51006 is made available to update the percent complete in P511112 (Update Percent Complete).  In 9.0 all jobs were shown here, and the user could update multiple jobs at once.  The functionality from 9.0 should be the same in 9.2.

Changes

 

Cause